Clusters
• Construction is 80% complete.
• Target is the main contractor.
• Finishing is progressing well.
• Handover will take place by end of 2009.
• Landscape has started and is planned to be finished in unison with handover.
Fronds
• Construction in Towers A & D is progressing well.
• Slab work has reached the 11th floor.
• Approximately 1 floor is completed every 2 weeks.
-
LOA letter of acceptance has been signed for both Al Shafaar and CCC
Our biggest landmark to date is that we have signed a letter of Acceptance with Consolidated .....
-
Clusters started to take its shape!!
Significant progress has already been made in both the East and West sectors. And the roof .....